| Construction Progress as on May 14 2012 | ||
|
Clubhouse : civil work completed MEP work in progress |
Block B | Handing over starts from June. Lift work in progress |
| Construction Progress as on May 5 2012 | ||
| ATM Security Room | Swimming Pool | External painting internal finishes in Progress |